PROJECT DETAILS
Client: Cedar College
Location: 215-233 Fosters Rd, Northgate, SA, 5085
Project Size: 200 KW
Product Details: Trina 280 W Poly silver Frame modules × 714
SMA STP 50 kW 3 Phase 6 MPPT Core 1 Grid Connect (STP 50-40) × 2
SMA STP 20.0TL 3 Phase 2 MPPT (STP20000TL-30) × 2
SMA STP 15.0TL 3 Phase 2 MPPT (STP 15000TL-30) × 1
Description: Cedar college’s transition to the clean energy will reduce their dependence on the electricity grid. The 200 KW Solar PV system offers sustainable long-term savings. The cedar college will save the significant amount on the utility bills by using solar energy. The total energy consumption of the Cedar college is fulfilled by this project because Cedar college is operated during the daytime.